Back to overview
10 kV Substation IJmuiden
As part of infrastructure upgrades in the IJmuiden region, BHP Funderingstechniek contributed to the development of a 10 kV substation, in commission of Liander and in collaboration with the construction joint venture K_Dekker / Tervoort.
Project Details
-
Foundation type: Screw‑in injection piles
-
Number of piles installed: 47
-
Pile diameter: ø 273 mm or ø 350 mm
-
Pile length: Approximately 5 m
-
Client: Liander
-
Main contractor: K_Dekker / Tervoort Construction JV
These screw‑in injection piles were chosen for their durability and efficiency, allowing for minimal site disturbance while ensuring a sturdy foundation for the electrical infrastructure.