At the Schiermonnikoog site, BHP Funderingstechniek contributed to the construction of the new LOC Schiermonnikoog. For this project, we proudly supplied and installed 84 mortar-screw piles, essential for a robust foundation.
Number of piles: 84
Type: Mortar-screw piles
Diameter: Ø 400 mm
Length: 15.5 m
Installation machine: Junttan PM 16 — chosen for its precision, efficiency, and reliability in the delicate environment of Schiermonnikoog.
Client: Municipality of Schiermonnikoog
Main contractor: Friso Bouwgroep B.V.
The collaboration emphasized sustainability and minimizing environmental impact, aligning with project goals in this protected natural area. At BHP Funderingstechniek, we are proud to have supported key infrastructure in Schiermonnikoog and look forward to future technically challenging projects.