BHP Funderingstechniek delivered the foundation works for a new 10 kV electrical substation located at Sextantweg 150. The project was commissioned by Liander and executed in collaboration with a joint venture of K_Dekker and Tervoort.
Project Details:
Foundation type: Screw‑in injection piles
Number of piles installed: 53
Pile diameters: Ø 273 mm and Ø 350 mm
Pile length: Approximately 5 m per pile
Installation equipment: Precision-driven machinery optimized for minimal disturbance
Client: Liander
Main contractor: K_Dekker & Tervoort JV
The injection piles provided a strong and efficient foundation solution, well-suited for utility infrastructure while ensuring minimal soil and site impact.