Sub-Foundation for LM Hall – Lankhorst Sneek
In 2023, BHP Funderingstechniek carried out the foundation work for the LM Hall in Sneek. The project was commissioned by Lankhorst Sneek BV and executed in collaboration with Schotanus Betonbouw.
BHP was responsible for supplying and installing 205 internally driven steel tube piles, tailored to meet the technical requirements of the hall’s substructure.
Project Details:
- Number of piles: 205
- Pile diameter: Ø 273 mm
- Pile length: 6 to 7 metres
- Installation equipment: Vermeer 1200 drilling machine with Ecodrie 2500
Thanks to thorough preparation and efficient execution, the foundation was completed on time and to a high standard. The result is a solid base for the further construction of the LM Hall.